Water management solutions
Technological equipment for wastewater treatment
Šafov
Delivery kind: Technological equipment for wastewater treatment
Place: Šafov
Capacity: 150 PE
Commissioned: 3/2023
Technological equipment for wastewater treatment
Zbraslav
Delivery kind: Technological equipment for wastewater treatment
Place: Zbraslav
Capacity: 1560 PE
Commissioned: 3/2023
Technological equipment for wastewater treatment
Radkovice u Hrotovic
Delivery kind: Technological equipment for wastewater treatment plant and a pumping station
Place: Radkovice u Hrotovic
Capacity: 400 PE
Commissioned: 10/2022
Technological equipment for wastewater treatment
Příbram na Moravě
Delivery kind: Technological equipment for wastewater treatment plant and a pumping station
Place: Příbram na Moravě
Capacity: 700 PE
Commissioned: 10/2022
Technological equipment for wastewater treatment
Rusava
Delivery kind: Technological equipment for wastewater treatment
Place: Rusava
Capacity: 1500 PE
Commissioned: 9/2022
Modernization of sludge pipeline ending
Hodonín
Delivery kind: General delivery
Place: Hodonín
Processing of condensed sludge:
max 30 m3/h, out. concentration. 5-8%
Processing of dewatered sludge:
max 30 m3/h, out. concentration. 25-35%
Dewatered sludge pumping: 1 - 3 m3/h
Commissioned: 4/2022
Reconstruction of wastewater treatment plant
Rajhrad
Delivery kind: Technological equipment for wastewater treatment
Place: Rajhrad
Capacity: 6000 PE
Commissioned: 2/2022
Wastewater treatment plant intensification
Římov
Delivery kind: Construction and technological works
Place: Římov
Capacity: 625 PE
Commissioned: 10/2021
Wastewater treatment plant intensification
Hodonice
Delivery kind: Technological equipment
Place: Hodonice
Capacity: 5 000 PE
Commissioned: 08/2021
Wastewater treatment plant enlargement
Holubice
Delivery kind: Technological equipment
Place: Holubice
Capacity: 2 762 PE
Commissioned: 7/2021
Wastewater treatment plant reconstruction
Havlíčkův Brod
Delivery kind: Construction and technological equipment
Place: Havlíčkův Brod
Thermal output: 173,85 kW
Commissioned: 05/2021
Wastewater treatment plant modernization
Rájec-Jestřebí
Delivery kind: Completion and modernization
Place: Rájec-Jestřebí
Capacity: 4 300 PE
Commissioned: 04/2021
Wastewater treatment plant modernization
Popovice
Delivery kind: Completion and modernization
Place: Popovice
Capacity: 600 PE
Commissioned: 09/2020
Wastewater treatment plant enlargement
Perná
Delivery kind: Construction and technology
Place: Perná
Capacity: 300 PE
Commissioned: 01/2020
Wastewater treatment plant reconstruction
Štoky
Delivery kind: Technological equipment
Place: Štoky
Capacity: 1 900 PE
Commissioned: 01/2020
Technological equipment for wastewater treatment plant
Heřmanov
Delivery kind: Technological equipment
Place: Heřmanov
Capacity: 250 PE
Commissioned: 11/2019
Wastewater treatment plant reconstruction
Brno - Modřice
Delivery kind: Technological equipment
Place: Brno
Capacity: 16 700 Nm3/hour
Commissioned: 9/2019
Wastewater treatment plant reconstruction
Měřín
Delivery kind: Technological equipment
Place: Měřín
Capacity: 3 570 PE
Commissioned: 07/2019
Wastewater treatment plant for ŽĎAS, a.s.
Žďár nad Sázavou
Delivery kind: Technological equipment
Place: Žďár nad Sázavou
Capacity: 1 950 PE
Commissioned: 09/2016
Wastewater treatment plant intensification and enlargement
Poděbrady
Delivery kind: Technological equipment
Place: Poděbrady
Capacity: 38 200 PE
Commissioned: 6/2016
Technological equipment for wastewater treatment and pumping station
Hostěradice
Delivery kind: Technological equipment
Place: Hostěradice, Skalice, Morašice
Capacity: 2 800 PE
Commissioned: 12/2015